Bheri Babai irrigation, hydropower project pushed back further
kathmandupost.com · Sat Mar 29 03:05:28 GMT 2025

The project aims to provide year-round irrigation to 51,000 hectares in two districts and produce 48-megawatt electricity.
The completion of the Bheri Babai Diversion Multipurpose Project, a national pride initiative in mid-western Nepal, has been delayed by four more years. Originally slated to complete in 2024, the project has achieved only 51 percent physical progress.
Read full story at source (kathmandupost.com)