Rahughat Hydropower Project Resumes Production After 11-Day Repair
english.ratopati.com · Thu Oct 08 11:19:04 GMT 2026

Kathmandu. The Rahughat Hydropower Project, damaged by floods in the Kaligandaki River, has resumed electricity production after repairs were completed in just 11 days.
The powerhouse was submerged due to the flood on Asauj 11, causing damage to important structures and equipment. After completing the necessary repairs and technical work, one unit of the project with a capacity of 20 megawatts was brought into operation from Thursday.