Chuhar Bridge Construction Process Advances with Increased Budget

english.ratopati.com · Sun Oct 25 01:15:00 GMT 2026

Biratnagar. The process of constructing the much-talked-about 'Chuhar Bridge' over the Dudh Koshi River, connecting Udayapur and Bhojpur, which has been mired in controversy and delays for a long time, has moved forward. The Directorate of Infrastructure Development, Itahari has approved a variation order, increasing the cost of bridge construction by 22.85 percent.

Milan Acharya, Secretary of the Ministry of Physical Infrastructure Development, Koshi Province, has approved the variation change, adding more than 4 crore 85 lakh rupees to the contract of the construction company 'Kalika Pacific Joint Venture'.

Read full story at source (english.ratopati.com)