Mid hill highway’s Parbat section works resume
english.ratopati.com
Kathmandu - The construction works of Parbat section along the mid-hill highway – which were stalled following the coronavirus pandemic have resumed now. As informed the construction process that has been halted since March 21 has resumed after a hiatus. The Lama Construction Company which was awarded the contract for the construction of the Parbat section of the mid-hill highway began its works after the letup in rain.
Though the contract period for the construction expired in mid-September, only 60 percent progress has been made so far. “Lockdown halted the construction works but now it has taken its speed”, project manager of the Construction Company Govinda Bhusal said. He also shared that the blacktopping would be initiated after the Dashain.