22.5 MW Upper Thulokhola Hydropower Project Connects to National Grid After Successful Testing
english.ratopati.com · Sun Mar 15 01:57:39 GMT 2026

Myagdi. Electricity generated from the 22.5 megawatt capacity 'Upper Thulokhola' hydropower project has been connected to the central transmission line.
The physical structure construction, equipment installation, and internal testing of the project, built by Thulokhola Hydropower Limited in Raghuganga Rural Municipality-7, have been completed, and electricity has been fed into the central line. Project Chief Shiva Sagar Yadav informed that testing for transmission to the central line began on the evening of Falgun 29 at 6:00 PM.