Cabinet delay leaves key expressway section in limbo in Khokana

kathmandupost.com · Sun Apr 19 00:58:52 GMT 2026

Proposal to shift toll plaza to Pharsidol awaits Cabinet decision as construction reaches 46.88 percent, Mahadevtar tunnel breakthrough targeted by mid-July.

The government remains undecided on a proposal to relocate the toll plaza of the Kathmandu-Tarai Expressway to Pharsidol, leaving construction work in the Khokana section of Lalitpur stalled. The lack of a formal decision has halted all activities in the disputed stretch, even as progress continues in other sections of the national pride project.