Four-lane bridge construction in Damuali reaches 84% physical progress
english.ratopati.com · Sat May 16 08:53:22 GMT 2026

Tanahun. The physical progress of the four-lane bridge being constructed in Damuali bazaar along the Muglin Pokhara road section has reached 84 percent. The economic progress of the bridge being constructed over the Madi River in Vyas Municipality-4 and 5 has reached 81.2 percent.
The engineer of the section, Bishnu Prasad Pandey, informed that the bridge construction is progressing at a rapid pace, and the foundation work on both sides has been completed, with the arch design currently under construction. According to him, the work on the bridge, which was started with the aim of completing construction within three years, had its contract deadline expired on last Bhadra 21, and the deadline has been extended until next Asar 19.